BRIEF DESCRIPTION
The Dredging & Rock Removal project was contract #8 Reach B as part of the Delaware River Main Channel Deepening. The overall project is part of the Delaware River Federal Navigation Channel which reaches from Philadelphia Harbor to Delaware Bay, a partnership between USACE and Philadelphia Regional Port Authority.
Dredging is located from the Eddystone Range to the Marcus Hook Range of the Delaware River. Material is both mechanically dredged and loaded into scows for off-site disposal or the use of controlled underwater blasting is applied to break up hard rock and disposed offsite.
TITAN performed quality control management for this project. In addition TITAN handled reviewing, scheduling, certifying and managing the submittals through the 3-Phase process of inspection.
Procedures for tracking preparatory, initial, and follow-up control phases; control, verification, and acceptance tests including documentation.
Coordination of project logistics, materials and equipment
Managing the day-to-day quality control activities
Kept designated personnel and management staff apprised of status of work
Ensured all reports were prepared and submitted in accordance with the QC Plan, including the Daily Quality Control Report and through the QCS/RMS system.
Maintained all the project quality control files.
Reported and logged any work not meeting Spec requirements.
Recorded all data in QCS database.
AT A GLANCE
Project Type | Deepening |
TITAN Role | Quality Control Management |
Client | Great Lakes Dredge & Dock |
Completion Date | December 2017 |
Project Size | 320,000 Cubic Yards |
Contract Value | $76.8 |
Questions About TITAN Personnel
Does your personnel know the process to work on federal projects?
We know the processes of working with multiple government departments and multiple districts within those departments. Our work primarily involves working with USACE, NAVFAC, Department of Veteran Affairs, Air Force, and GSA.
How much notice is needed in order for you to mobilize to the job?
In many cases, we can be there within a couple days. Our company structure is designed to accommodate the challenging and demanding dredging industry.
What is included in TITAN personnel proposals?
We cover everything needed to get our personnel to your jobsite and keep them there and provide you with a simplistic invoice at the end of the month. Working with TITAN couldn’t be easier!