BRIEF DESCRIPTION
Contract #: W912WJ-18-C-0037. This project was for dredging an area of the Federal navigation chanel near the entrance of the Saco River. The dredging work includes an 8-foot-deep entrance channel and three 6-foot-deep anchorages.
Total yardage to be dredged and removed was approximately 41,000 cubic yards, with another 36,000 cubic yards of 1 foot allowable over depth.
Titan Provided a Site Safety and Health Officer (SSHO) to the project
AT A GLANCE
Project Type | maintenance |
TITAN Role | Site Safety and Health Officer (SSHO) |
Client | Southwind Construction |
Does your personnel know the process to work on federal projects?
We know the processes of working with multiple government departments and multiple districts within those departments. Our work primarily involves working with USACE, NAVFAC, Department of Veteran Affairs, Air Force, and GSA.
How much notice is needed in order for you to mobilize to the job?
In many cases, we can be there within a couple days. Our company structure is designed to accommodate the challenging and demanding dredging industry.
What is included in TITAN personnel proposals?