BRIEF DESCRIPTION
The work will consist of maintenance dredging of Ft. Myers Beach Harbor, Lee County, Ft. Myers Beach, Florida.
The Federal Channel will be dredged to a 12-foot required depth plus 2 feet of allowable overdepth. All dredged material will be placed in the nearshore disposal area located approximately a quarter mile east from Ft. Myers Beach Pier. Maximum pumping distance will be approximately 3.5 miles.
Work also includes turbidity monitoring and environmental protection activities.
AT A GLANCE
Project Type | Maintenance Dredging |
TITAN Role | Quality Control Management and SSHO |
Client | H & L Contracting |
Job Duration / Completion Date | 2 Months / February 2015 |
Project Size | 80,110 cubic yards |
Contract Value | $2.5M |
SCOPE OF WORK
Work under this contract consisted of:
- Quality control and site safety
- Scheduling, reviewing, certifying, and managing all submittals through the three phase process of inspection
- Procedures for tracking preparatory, initial, and follow-up control phases
- Control, verification, and acceptance tests including documentation
- Coordination of project logistics, materials, and equipment
- Managing the day-to-day quality control activities
- Managed safety aspects of the job
Questions About TITAN Personnel
Does your personnel know the process to work on federal projects?
We know the processes of working with multiple government departments and multiple districts within those departments. Our work primarily involves working with USACE, NAVFAC, Department of Veteran Affairs, Air Force, and GSA.
How much notice is needed in order for you to mobilize to the job?
In many cases, we can be there within a couple days. Our company structure is designed to accommodate the challenging and demanding dredging industry.
What is included in TITAN personnel proposals?
We cover everything needed to get our personnel to your jobsite and keep them there and provide you with a simplistic invoice at the end of the month. Working with TITAN couldn’t be easier!