BRIEF DESCRIPTION
This project was a Congressionally-authorized Federal Navigation Project (FNP) in Little Narragansett Bay, Westerly, RI and Stonington, CT. Approximately 60,000 cubic yards of sandy material was dredged from the channel and placed onto Sandy Point Island. A hydraulic cutter head dredge removed sandy material from the shoaled portions of the Little Narragansett Bay Federal Navigation Channel and pumped it onto the island where it was graded per contract drawings. Placement on the island included a maximum elevation of 7.5 feet above MLLW and a 1 foot vertical to 10 foot horizontal slope extending from the center portion of the island into the intertidal zone.
Services provided by TITAN under this contract consisted of dredging quality control and site safety along with scheduling, reviewing, certifying, and managing of all submittals through the three phase process of inspection.
AT A GLANCE
Project Type | Shoal Removal |
TITAN Role | Quality Control Management and SSHO |
Client | H & L Contracting |
Job Duration / Completion Date | 2 Months / January 2015 |
Project Size | 60,000 cubic yards |
Contract Value | $1.5M |
SCOPE OF WORK
Work under this contract consisted of:
- Quality control and site safety
- Scheduling, reviewing, certifying, and managing all submittals through the three phase process of inspection
- Procedures for tracking preparatory, initial, and follow-up control phases
- Control, verification, and acceptance tests including documentation
- Coordination of project logistics, materials, and equipment
- Managing the day-to-day quality control activities
- Managed safety aspects of the job
Questions About TITAN Personnel
Does your personnel know the process to work on federal projects?
We know the processes of working with multiple government departments and multiple districts within those departments. Our work primarily involves working with USACE, NAVFAC, Department of Veteran Affairs, Air Force, and GSA.
How much notice is needed in order for you to mobilize to the job?
In many cases, we can be there within a couple days. Our company structure is designed to accommodate the challenging and demanding dredging industry.
What is included in TITAN personnel proposals?
We cover everything needed to get our personnel to your jobsite and keep them there and provide you with a simplistic invoice at the end of the month. Working with TITAN couldn’t be easier!